Articles tagged under: NHSRCL

Railway Minister reviews progress of Bilimora station of Mumbai-Ahmedabad Bullet Train project

October 13, 2025
Railway Minister reviews progress of Bilimora station of Mumbai-Ahmedabad Bullet Train project

Navsari: Union Minister of Railways, Ashwini Vaishnaw, visited the under-construction Bilimora Bullet Train station of the Mumbai-Ahmedabad Bullet Train project today. He was accompanied by Dhaval Patel, Member of Parliament – Valsad, and Naresh Patel, Member of Legislative Assembly – Gandevi. During the visit, the minister reviewed the ongoing construction and track-laying works at the Bilimora Bullet Train station. Bilimora Bullet Train Station Bilimora city is famous for its Mango Orc...Read More

Breakthrough in Maharashtra for Mumbai Ahmedabad Bullet Train Corridor

September 07, 2025
Breakthrough in Maharashtra for Mumbai Ahmedabad Bullet Train Corridor

Mumbai: The National High-Speed Rail Corporation Limited (NHSRCL) has successfully launched the first Full Span Pre-Stressed Concrete (PSC) Box Girder of 40 meters length through the full span launching gantry (FSLG) in the Maharashtra section of the Mumbai-Ahmedabad Bullet Train corridor, at Sakhare Village, Dahanu (Maharashtra) on 6th September 2025. The Maharashtra section of the Bullet Train corridor is 156 km long which includes 135 km of elevated alignment from Shilphata till Zaroli villa...Read More

Bullet train project: NHSRCL completes 200-metre steel bridge over NH-48 in Gujarat

September 04, 2025
Bullet train project: NHSRCL completes 200-metre steel bridge over NH-48 in Gujarat

Anand: The National High-Speed Rail Corporation Limited (NHSRCL) has completed the ninth steel bridge on the Gujarat section of the Mumbai–Ahmedabad High-Speed Rail (MAHSR) bullet train corridor. The new structure, spanning 200 meters across National Highway 48 in Anand district, consists of two steel spans of 100 meters each. In a press release, NHSRCL said: "The second 100 m span of the 2 × 100 m long steel bridge was successfully launched over NH-48 (connecting Delhi, Mumbai & Chennai...Read More

Bullet Train Project: Vishwamitri River Bridge in Vadodara Now Complete

August 06, 2025
Bullet Train Project: Vishwamitri River Bridge in Vadodara Now Complete

Vadodara: The construction of the river bridge over the Vishwamitri River in Vadodara district has been completed as part of the Mumbai-Ahmedabad Bullet Train corridor. This marks the completion of the 17th out of 25 planned river bridges for the high-speed rail project, according to an announcement by the National High-Speed Rail Corporation Limited (NHSRCL) today. Of the total 25 bridges, 21 are located in Gujarat and the remaining four in Maharashtra. Spanning 80 meters, the bridge is locat...Read More

Bullet Train Project: Nearly 200 km of Track Slabs Cast in Gujarat

May 28, 2025
Bullet Train Project: Nearly 200 km of Track Slabs Cast in Gujarat

Ahmedabad: The construction of the Mumbai-Ahmedabad High-Speed Rail corridor has gathered pace, with track laying work progressing steadily in Gujarat. According to  National High Speed Rail Corporation Limited (NHSRCL), the installation of track slab and CAM (Cement Asphalt Mortar) filling have commenced on the viaduct at different locations in Gujarat. Around 160 track km of track bed construction has been achieved so far in Gujarat. Around 39,500 track slabs have been cast, which are equiv...Read More

Bullet Train Project: 70-meter long steel bridge launched over DFCCIL tracks near Vadodara

April 09, 2025
Bullet Train Project: 70-meter long steel bridge launched over DFCCIL tracks near Vadodara

Vadodara: A steel bridge of 70 m length was successfully launched over the two DFCCIL tracks near Vadodara on 8th April 2025 for Mumbai-Ahmedabad Bullet Train project. This is the seventh steel bridge completed for the project in Gujarat out of the planned 28 steel bridges for the entire corridor. The construction of these seven steel bridges have utilized over 10,000 metric tons of steel providing a significant boost to the steel industries in India. This 674 MT steel bridge of 13 m in height...Read More

List of trains affected as Gantry falls at NHSRCL site at Geratpur – Vatva section of Ahmedabad

March 24, 2025
List of trains affected as Gantry falls at NHSRCL site at Geratpur – Vatva section of Ahmedabad

Ahmedabad: A segmental launching gantry used for viaduct construction at the Mumbai-Ahmedabad bullet train project site in Vatva accidentally slipped from its position late Sunday night, affecting the adjoining railway line. The incident occurred around 11 PM while the gantry was retracting after launching a concrete girder. Senior officials from the National High-Speed Rail Corporation Limited (NHSRCL), along with police and fire service personnel, are on-site monitoring the situation. No casu...Read More

5th PSC Bridge Completed for Bullet Train Project in Gujarat

February 25, 2025
5th PSC Bridge Completed for Bullet Train Project in Gujarat

Surat: A 260 m long PSC bridge over National Expressway- 4 near Kosamba, Surat district is completed on 22nd February 2025 for Mumbai-Ahmedabad Bullet Train Project. The project is crossing over National Expressway- 4 between Delhi & Mumbai (passing through Rajasthan & Gujarat) near Kosamba at Surat district, Gujarat through elevated viaduct. The bridge features 104 precast segments with four spans of configuration 50m + 80m + 80m + 50m and was built using the B...Read More

Bullet Train Project: 100-Meter-Long Steel Bridge Launched Over Four Railway Tracks in Surat

February 06, 2025
Bullet Train Project: 100-Meter-Long Steel Bridge Launched Over Four Railway Tracks in Surat

Surat: National High Speed Rail Corporation Limited has launched a steel bridge over four railway tracks; two of western railways and two DFC tracks between Kim & Sayan for Mumbai-Ahmedabad Bullet Train project. The bridge comprises of two spans; 100 m, 60 m and will facilitate double line Standard Gauge rail track. This crucial infrastructure development involved the crossing of four major tracks- two western railways and two DFC tracks and an irrigation canal. The 100 m span was launche...Read More

Another 210 m long bridge crossing NH-48 in Gujarat is completed for Bullet Train Project

January 13, 2025
Another 210 m long bridge crossing NH-48 in Gujarat is completed for Bullet Train Project

Gandhinagar: A 210 m long PSC (Pre-stressed concrete) bridge designed to cross over National Highway-48 (Delhi-Chennai) at Dabhan village, near Nadiad, Kheda district, Gujarat is completed on 9th January 2025. The bridge comprises of 72 precast segments with four spans of configuration 40m + 65m + 65m + 40m and was built using  Balanced Cantilever Method, which is ideal for larger spans. This newly completed bridge is situated between Anand and Ahmedabad Bullet Train stations. Details of ...Read More