Delhi – Mumbai Expressway in Gujarat: Latest Package-wise Progress Update

Vadodara: Work on the 1,386 km-long, eight-lane Delhi-Mumbai Expressway is progressing rapidly. To streamline construction, the project has been divided into several sections and packages. This report provides a detailed update on the 426 km stretch passing through Gujarat.

In Gujarat, the expressway is divided into two key segments: Delhi to Vadodara and Vadodara to Virar. The Delhi to Vadodara stretch comprises 31 packages overall, with Packages 26 to 31 located within Gujarat—each at different stages of completion.

Package 26 begins in Madhya Pradesh, enters Gujarat near Chhayan village in Dahod district, and extends to Bhimpura village; so far, 70% of the work is complete. Package 27 continues from Bhimpura past the Limkheda Interchange to Sant Road and is 94% complete. Package 28, covering the stretch between Sant Road and the Godhra Interchange, has reached 95% completion.

Package 29, which connects the Godhra Interchange to the Kalol Interchange, is fully complete. Meanwhile, Package 30—from Kalol Interchange to Pratapnagar—stands at 94% completion, and Package 31, running from Pratapnagar to the Ahmedabad–Vadodara Expressway (NE1) Interchange at Dodka village in Vadodara district, is 96% complete.

The Vadodara to Virar section consists of 13 packages, with Packages 1 to 10 falling within Gujarat, starting from Vadodara and extending to the Maharashtra border.

In this segment, Packages 1, 2, and 3—which cover the Vadodara–Bharuch stretch—are now operational up to Dehgam village in Bharuch district, ensuring smooth connectivity. Package 4, from Manubar to Ankleshwar, is fully completed but has not yet been opened to traffic.

Packages 5 to 10 show varied progress: Package 5 (Ankleshwar to Kim Interchange) is 76% complete; Package 6 (Kim Interchange to Ena Interchange near Surat) is 100% complete and was temporarily opened last week. Package 7, covering about 28 km, is 92% finished.

However, progress is significantly slower in Packages 8, 9, and 10, which cover the Jujuwa to Talasari stretch in South Gujarat up to the Maharashtra border. Their completion levels stand at just 5%, 10%, and 96%, respectively. Notably, work on Package 8 has remained stalled at 5% since the last update in May.

Currently, only the Vadodara–Bharuch section and an additional 37 km stretch between Kim and Ena are open to traffic in Gujarat. While the central government had earlier informed Parliament that the entire expressway would be finished by October 2025, this target now seems unlikely. The ongoing monsoon has slowed construction further, and several packages are still far from completion. The only realistic hope for motorists is that the Vadodara to Surat stretch may open around Diwali, as it is nearly complete. DeshGujarat

Table 1: Work Progress on Delhi–Mumbai Expressway Packages in Gujarat

Package Length (km) Route Description Work Progress
🔹 Section – Delhi to Vadodara
Package 26 32.835 Gujarat–MP border to Bhimpura village (Dahod district) 70%
Package 27 26.352 Bhimpura village to Sant Road (near Panam River) 94%
Package 28 25.23 Sant Road to Godhra Interchange 95%
Package 29 22.5 Godhra Interchange to Kalol Interchange 100%
Package 30 21.5 Kalol Interchange to Pratapnagar (Vadodara district) 94%
Package 31 19.462 Pratapnagar to Ahmedabad–Vadodara Expressway (NE1) 96%
🔹 Section – Vadodara to Virar
Package 1 23.74 Vadodara–Bharuch segment (Operational) 100%
Package 2 32 Vadodara–Bharuch segment (Operational) 100%
Package 3 31 Vadodara–Bharuch to Manubar (Operational) 100%
Package 4 13 Manubar to Ankleshwar 100%
Package 5 24.57 Ankleshwar to Kim Interchange 76%
Package 6 36.93 Kim Interchange to Ena Interchange (near Surat) (Operational) 100%
Package 7 27.5 Ena Interchange to Kharel Interchange (near Gandeva) 92%
Package 8 35.4 Gandeva to Jujuwa 5%
Package 9 26.6 Jujuwa to Karvad 10%
Package 10 24.6 Karvad to Talasari Interchange (near Maharashtra border) 36%
Package Length (km) Start Date (Contractor) Work Progress
🔹 Section – Delhi to Vadodara
Package 26 32.835 02/05/2022 70%
Package 27 26.352 14/02/2022 94%
Package 28 25.23 16/11/2021 95%
Package 29 22.5 16/04/2021 100%
Package 30 21.5 08/09/2021 94%
Package 31 19.462 18/05/2021 96%
🔹 Section – Vadodara to Virar
Package 1 23.74 18/01/2019 100%
Package 2 32 31/01/2019 100%
Package 3 31 08/03/2019 100%
Package 4 13 10/12/2018 100%
Package 5 24.57 01/11/2019 76%
Package 6 36.93 11/12/2021 100%
Package 7 27.5 09/11/2021 92%
Package 8 35.4 31/08/2024 5%
Package 9 26.6 13/04/2024 10%
Package 10 24.6 22/03/2022 36%