26 Major Ongoing NHAI Highway Works in Gujarat: List and Progress Updates
June 04, 2025
New Delhi: According to the data shared by the National Highways Authority of India (NHAI), there are 26 major highway works currently under implementation in the state of Gujarat. These road infrastructure projects include two sections of the Delhi–Mumbai Expressway project, the Ahmedabad–Dholera Expressway project, and the upgradation of highways in the Saurashtra region, which will enhance commuter comfort and connectivity.
Key Projects Underway
1. Delhi–Vadodara Greenfield Expressway (NH-148N)
Among the flagship developments is the Delhi–Vadodara Greenfield Alignment, with multiple packages—such as Pkg-26, Pkg-27, and Pkg-28—making significant strides. The financial progress of these packages ranges from 59.75% to 94.37%, with major contractors like GHV (India) Pvt. Ltd. and Atlas Construction Pvt. Ltd.–NKC JV steering the implementation. These sections were scheduled for completion between August 2024 and November 2023 but have faced delays and are not yet complete as of June 2025.
2. Vadodara–Mumbai Expressway (NE-4)
Several packages of the Vadodara–Mumbai Expressway, including Kim to Ankleshwar, Gandeva to Ena, and Talsari to Karvad, are at various stages of implementation. While some sections, like the Gandeva to Ena stretch (Pkg VII), show over 90% completion, others, like Jujuwa to Gandeva (Pkg VIII), are still in the early phases. The expressway, once completed, will be a game-changer for trade and transit between Gujarat and Maharashtra.
3. Ahmedabad–Dholera Expressway (NH-751)
The Ahmedabad–Dholera Expressway, critical to connecting Gujarat’s first smart city—Dholera Special Investment Region (DSIR)—is progressing rapidly. With four packages spanning a total length of over 109 km, the expressway has seen financial progress of up to 96.95%. Work is being handled by Gawar Construction Ltd., GHV (India), and Dineshchandra R. Agrawal Infracon Pvt. Ltd.
4. Widening & Upgradation Projects
Other major projects include key upgradation works such as the Jetpur–Gondal–Rajkot six-laning and the NH-341 Bhuj Airport Corridor. The Sanchore–Santalpur stretch on NH-754K and the Patan–Gojariya section on NH-68 are among the high-progress projects, with completion percentages above 69%, ensuring that once complete, they will significantly improve intra-state connectivity.
| Under Implementation | |||||||||
| All Length in km. | |||||||||
| Sr. No. | Project Name | NH(New) | Total Length | Appointed Date/Start Date- Contractor | Financial Progress (%) As of June 1st | Scheduled Completion / Demobilization Date | Mode | Concessionaire | State |
| 1 | Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-26) (Ch.696+890 to Ch.726+390) |
NE-4 | 32.835 Km | 02/05/202 2 |
59.75 % | 31-08-2024 | EPC | Atlas Construction Pvt. Ltd. – NKC (JV) |
Gujarat |
| 2 | Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-27) (Ch.729.700 to Ch.756.052) |
NE-4 | 26.352 Km | 14/02/202 2 |
91.17 % | 14-02-2024 | EPC | GHV (India) Pvt Ltd. | Gujarat |
| 3 | Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-28) (Ch.756+052 to Ch.781+282) |
NE-4 | 25.23 Km | 16/11/202 1 |
94.37 % | 15-11-2023 | EPC | GHV (India) Pvt Ltd. | Gujarat |
| 4 | Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-30) (Ch 803+420 to Ch.824+920) [Baletiya Village – Junction near Pratap Nagar Village] |
NE-4 | 21.5 Km | 08/09/202 1 |
88.79 % | 07-09-2023 | EPC | Patel Infrastructure Limited | Gujarat |
| 5 | Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-31) (Ch.824+920 to Ch.844+382) [Junction near Pratap nagar Village – Junction near Dodka Village] |
NE-4 | 19.462 Km | 18/05/202 1 |
88.95 % | 18-05-2023 | EPC | PNC Infratech Pvt. Ltd. | Gujarat |
| 6 | Vadodara Mumbai Expressway (Kim to Ankleshwar) (Phase IA – Pkg V) |
TBD | 24.57 Km | 01/11/201 9 |
83.30 % | 31-10-2021 | HAM | Gawar kim expressway pvt. Ltd | Gujarat |
| 7 | Vadodara Mumbai Expressway (Gandeva to Ena) (Phase IB – Pkg VII) [Km 190.00 to Km 217.500] |
NE-4 | 27.5 Km | 09/11/202 1 |
90.56 % | 09-11-2023 | HAM | IRB Infrastructure Developers Ltd. | Gujarat |
| 8 | Vadodara Mumbai Expressway (Talsari to Karvad) (Phase IB – Pkg X) [Km 103.400 to Km 128.000] |
NE-4 | 24.6 Km | 22/03/202 2 |
35.50 % | 21-03-2024 | HAM | Roadway Solutions India Infra Ltd. | Gujarat |
| 9 | Vadodara Mumbai Expressway (Jujuwa – Gandeva) from Km. 154.600 to Km. 190.000 (Phase-I Package-VIII) | NE-4 | 35.4 Km | 31/08/202 4 |
3.50 % | 02-03-2026 | EPC | Roadway Solutions India Infra Ltd. | Gujarat |
| 10 | Vadodara Mumbai Expressway (Karvad – Jujuwa) from Km. 128.000 to Km. 154.600 (Phase-I Package-IX) | NE-4 | 26.6 Km | 13/04/202 4 |
14.45 % | 13-10-2025 | EPC | Roadway Solutions India Infra Ltd. | Gujarat |
| 11 | Ahmedabad – Dholera (Pkg I) from km. 0.00 to km. 22.00) [Sardar Patel Ring Road – Sindhrej Village] |
751 | 22 Km | 11/01/202 2 |
92.64 % | 10-01-2024 | EPC | Gawar Construction Ltd | Gujarat |
| 12 | Ahmedabad – Dholera (Pkg II) from km. 22.00 to km. 48.52) [Sindhrej Village – Vejallka Village] |
751 | 26.52 Km | 21/01/202 2 |
81.96 % | 21-01-2024 | EPC | Gawar Construction Ltd | Gujarat |
| 13 | Ahmedabad – Dholera (Pkg III) from km. 48.52 to km. 71.06) [Vejallka Village – Start of DSIR zone] |
751 | 22.54 Km | 20/07/202 1 |
96.95 % | 19-07-2023 | EPC | GHV (India) Pvt Ltd. | Gujarat |
| 14 | Ahmedabad – Dholera (Pkg IV) from km. 71.06 to km. 109.019) [Start of DSIR zone – Adhelai Village] |
751 | 37.959 Km | 13/12/202 1 |
95.80 % | 13-12-2023 | EPC | Dineshchandra R. Agrawal Infracon Pvt. Ltd. |
Gujarat |
| 15 | Construction of 20.56 km long Connecting road from Ch.0.000 to Ch.20.560 parallel and LHS to Dholera – Bavaliyari section of Ahmedabad – Dholera Expressway (NH-751) in the state of Gujarat on EPC Mode | NE-8 | 20.56 Km | 20/02/202 5 |
New | New | EPC | Khurana Engineering Ltd | Gujarat |
| 16 | 6L of Shamla ji to Motachilodha from km.401.200 to km. 494.410 of Old NH-8 (Pkg-VI) |
48 | 93.21 Km | 02/01/201 9 |
83.84 % | 01-01-2021 | HAM | Chetak Enterprises Pvt Limited | Gujarat |
| 17 | Widening to 6L of Existing 4L Jetpur – Gondal – Rajkot Section from Km. 117.600 to Km. 185.00 on NH-27 |
27 | 67.4 Km | 27/09/202 3 |
35.96 % | 26-09-2025 | EPC | Engineering Projects (India) Ltd. – Varaha Infra Limited (JV) |
Gujarat |
| 18 | 6L with PS of Samakhiyali to Santalpur section from km. 339.700 to Km. 430.100 of NH-27 |
27 | 90.9 Km | 28/12/202 3 |
31.40 % | 27-12-2025 | BOT Toll | IRB Infrastructure Developers Ltd. | Gujarat |
| 19 | Sanchore – Santalpur from km 67.000 – km 99.000 of NH- 754K (AJ-RGBS-Package-3) |
754K | 32 Km | 10/08/202 1 |
97.87 % | 09-08-2023 | EPC | SKS Infra Projects Pvt. Ltd. – KRC Infra Projects Pvt. Ltd. (JV) |
Gujarat |
| 20 | Sanchore – Santalpur from km 99.000 – km 130.073 of NH-754K (AJ-RGBS-Package-4) |
754K | 31.07 Km | 10/03/202 1 |
97.91 % | 09-03-2023 | EPC | CDS Infra Projects Limited | Gujarat |
| 21 | 4L of Dhrol bypass section of NH-151A (Approx. length 5.7 Km) & widening upto 4 laning of missing link of Amran section of NH-151A (Approx. length 6.55 Km) from existing Ch. 42+000 to 48+500 of ongoing Dhrol-Bhadra- Pipaliya section of NH-151A |
151A | 12.25 Km | 03/02/202 5 |
0.00 % | 02-02-2027 | EPC | MKC Infrastructure Ltd. | Gujarat |
| 22 | Upgradation to 4L PS from Bhimasar, Junction of NH-41 to Anjar- Bhuj upto Airport Junction from Km 0.000 to Km 65.478 of NH-341 |
341 | 59.538 Km | 02/01/202 3 |
83.06 % | 29-06-2025 | HAM | G R Infraprojects Limited | Gujarat |
| 23 | 4L Kodinar – Veraval (Package VI) from km. 222.400 to km. 230.00 (Kodinar Bypass) of NH-8E (NH 51 new) | 51 | 7.6 Km | 22/04/202 2 |
93.94 % | 20-09-2023 | Item Rate | Kalthia Engineering & Construction Ltd. | Gujarat |
| 24 | 4L of Bal Works of Mahuva to Kagvadar from 100.450 Km. to 140.470 Km. of NH-8E (Pkg- III) |
51 | 40.02 Km | 24/03/202 1 |
94.00 % | 23-09-2022 | Item Rate | KCC Buildcon Pvt. Ltd. | Gujarat |
| 25 | 4L of Bal Works of Talaja – Mahuva from 54.990 km. to 100.450 km. of Old NH-8E (Package-II) |
51 | 45.46 Km | 24/03/202 1 |
97.13 % | 24-09-2022 | Item Rate | Kalthia Engineering & Construction Ltd. |
Gujarat |
| 26 | 4L PS Divided Carriageway from Patan (Near Rajpur) to Gojariya From Km 52.000 to Km 128.940 of NH-68 | 68 | 76.94 Km | 09/03/202 3 |
69.53 % | 07-03-2025 | EPC | WAGAD INFRAPROJECTS PVT. LTD. – RACHANA INFRASTRUCTURE LIMITED (JV) |
Gujarat |
Recent Stories
- India vs SL Match
- Free rides on AMTS buses for three days during Diwali
- 100 years of service to nation was our duty, so no celebration is needed: RSS Chief
- Commonwealth Sport Board Recommends Ahmedabad as Host City for 2030 Commonwealth Games
- Gujarat CM to visit Mumbai for listing of SMC's green municipal bonds on NSE