26 Major Ongoing NHAI Highway Works in Gujarat: List and Progress Updates

New Delhi: According to the data shared by the National Highways Authority of India (NHAI), there are 26 major highway works currently under implementation in the state of Gujarat. These road infrastructure projects include two sections of the Delhi–Mumbai Expressway project, the Ahmedabad–Dholera Expressway project, and the upgradation of highways in the Saurashtra region, which will enhance commuter comfort and connectivity.

Key Projects Underway

1. Delhi–Vadodara Greenfield Expressway (NH-148N)

Among the flagship developments is the Delhi–Vadodara Greenfield Alignment, with multiple packages—such as Pkg-26, Pkg-27, and Pkg-28—making significant strides. The financial progress of these packages ranges from 59.75% to 94.37%, with major contractors like GHV (India) Pvt. Ltd. and Atlas Construction Pvt. Ltd.–NKC JV steering the implementation. These sections were scheduled for completion between August 2024 and November 2023 but have faced delays and are not yet complete as of June 2025.

2. Vadodara–Mumbai Expressway (NE-4)

Several packages of the Vadodara–Mumbai Expressway, including Kim to Ankleshwar, Gandeva to Ena, and Talsari to Karvad, are at various stages of implementation. While some sections, like the Gandeva to Ena stretch (Pkg VII), show over 90% completion, others, like Jujuwa to Gandeva (Pkg VIII), are still in the early phases. The expressway, once completed, will be a game-changer for trade and transit between Gujarat and Maharashtra.

3. Ahmedabad–Dholera Expressway (NH-751)

The Ahmedabad–Dholera Expressway, critical to connecting Gujarat’s first smart city—Dholera Special Investment Region (DSIR)—is progressing rapidly. With four packages spanning a total length of over 109 km, the expressway has seen financial progress of up to 96.95%. Work is being handled by Gawar Construction Ltd., GHV (India), and Dineshchandra R. Agrawal Infracon Pvt. Ltd.

4. Widening & Upgradation Projects

Other major projects include key upgradation works such as the Jetpur–Gondal–Rajkot six-laning and the NH-341 Bhuj Airport Corridor. The Sanchore–Santalpur stretch on NH-754K and the Patan–Gojariya section on NH-68 are among the high-progress projects, with completion percentages above 69%, ensuring that once complete, they will significantly improve intra-state connectivity.

Under Implementation
All Length in km.
Sr. No. Project Name NH(New) Total Length Appointed Date/Start Date- Contractor Financial Progress (%) As of June 1st Scheduled Completion / Demobilization Date Mode Concessionaire State
1 Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-26)
(Ch.696+890 to Ch.726+390)
NE-4 32.835 Km 02/05/202
2
59.75 % 31-08-2024 EPC Atlas Construction Pvt. Ltd. – NKC
(JV)
Gujarat
2 Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-27)
(Ch.729.700 to Ch.756.052)
NE-4 26.352 Km 14/02/202
2
91.17 % 14-02-2024 EPC GHV (India) Pvt Ltd. Gujarat
3 Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-28)
(Ch.756+052 to Ch.781+282)
NE-4 25.23 Km 16/11/202
1
94.37 % 15-11-2023 EPC GHV (India) Pvt Ltd. Gujarat
4 Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-30) (Ch 803+420 to Ch.824+920) [Baletiya Village – Junction
near Pratap Nagar Village]
NE-4 21.5 Km 08/09/202
1
88.79 % 07-09-2023 EPC Patel Infrastructure Limited Gujarat
5 Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-31)
(Ch.824+920 to Ch.844+382) [Junction near Pratap nagar Village – Junction near Dodka Village]
NE-4 19.462 Km 18/05/202
1
88.95 % 18-05-2023 EPC PNC Infratech Pvt. Ltd. Gujarat
6 Vadodara Mumbai Expressway (Kim to Ankleshwar)
(Phase IA – Pkg V)
TBD 24.57 Km 01/11/201
9
83.30 % 31-10-2021 HAM Gawar kim expressway pvt. Ltd Gujarat
7 Vadodara Mumbai Expressway (Gandeva to Ena) (Phase
IB – Pkg VII) [Km 190.00 to Km 217.500]
NE-4 27.5 Km 09/11/202
1
90.56 % 09-11-2023 HAM IRB Infrastructure Developers Ltd. Gujarat
8 Vadodara Mumbai Expressway (Talsari to Karvad) (Phase
IB – Pkg X) [Km 103.400 to Km 128.000]
NE-4 24.6 Km 22/03/202
2
35.50 % 21-03-2024 HAM Roadway Solutions India Infra Ltd. Gujarat
9 Vadodara Mumbai Expressway (Jujuwa – Gandeva) from Km. 154.600 to Km. 190.000 (Phase-I Package-VIII) NE-4 35.4 Km 31/08/202
4
3.50 % 02-03-2026 EPC Roadway Solutions India Infra Ltd. Gujarat
10 Vadodara Mumbai Expressway (Karvad – Jujuwa) from Km. 128.000 to Km. 154.600 (Phase-I Package-IX) NE-4 26.6 Km 13/04/202
4
14.45 % 13-10-2025 EPC Roadway Solutions India Infra Ltd. Gujarat
11 Ahmedabad – Dholera (Pkg I) from km. 0.00 to km. 22.00)
[Sardar Patel Ring Road – Sindhrej Village]
751 22 Km 11/01/202
2
92.64 % 10-01-2024 EPC Gawar Construction Ltd Gujarat
12 Ahmedabad – Dholera (Pkg II) from km. 22.00 to km.
48.52) [Sindhrej Village – Vejallka Village]
751 26.52 Km 21/01/202
2
81.96 % 21-01-2024 EPC Gawar Construction Ltd Gujarat
13 Ahmedabad – Dholera (Pkg III) from km. 48.52 to km.
71.06) [Vejallka Village – Start of DSIR zone]
751 22.54 Km 20/07/202
1
96.95 % 19-07-2023 EPC GHV (India) Pvt Ltd. Gujarat
14 Ahmedabad – Dholera (Pkg IV) from km. 71.06 to km.
109.019) [Start of DSIR zone – Adhelai Village]
751 37.959 Km 13/12/202
1
95.80 % 13-12-2023 EPC Dineshchandra R. Agrawal Infracon
Pvt. Ltd.
Gujarat
15 Construction of 20.56 km long Connecting road from Ch.0.000 to Ch.20.560 parallel and LHS to Dholera – Bavaliyari section of Ahmedabad – Dholera Expressway (NH-751) in the state of Gujarat on EPC Mode NE-8 20.56 Km 20/02/202
5
New New EPC Khurana Engineering Ltd Gujarat
16 6L of Shamla ji to Motachilodha from km.401.200 to km.
494.410 of Old NH-8 (Pkg-VI)
48 93.21 Km 02/01/201
9
83.84 % 01-01-2021 HAM Chetak Enterprises Pvt Limited Gujarat
17 Widening to 6L of Existing 4L Jetpur – Gondal – Rajkot
Section from Km. 117.600 to Km. 185.00 on NH-27
27 67.4 Km 27/09/202
3
35.96 % 26-09-2025 EPC Engineering Projects (India) Ltd. –
Varaha Infra Limited (JV)
Gujarat
18 6L with PS of Samakhiyali to Santalpur section from km.
339.700 to Km. 430.100 of NH-27
27 90.9 Km 28/12/202
3
31.40 % 27-12-2025 BOT Toll IRB Infrastructure Developers Ltd. Gujarat
19 Sanchore – Santalpur from km 67.000 – km 99.000 of NH-
754K (AJ-RGBS-Package-3)
754K 32 Km 10/08/202
1
97.87 % 09-08-2023 EPC SKS Infra Projects Pvt. Ltd. – KRC Infra
Projects Pvt. Ltd. (JV)
Gujarat
20 Sanchore – Santalpur from km 99.000 – km 130.073 of
NH-754K (AJ-RGBS-Package-4)
754K 31.07 Km 10/03/202
1
97.91 % 09-03-2023 EPC CDS Infra Projects Limited Gujarat
21 4L of Dhrol bypass section of NH-151A (Approx. length  5.7 Km) & widening upto 4 laning of missing link of Amran section of NH-151A (Approx. length 6.55 Km) from existing Ch. 42+000 to 48+500 of ongoing Dhrol-Bhadra-
Pipaliya section of NH-151A
151A 12.25 Km 03/02/202
5
0.00 % 02-02-2027 EPC MKC Infrastructure Ltd. Gujarat
22 Upgradation to 4L PS  from Bhimasar, Junction of NH-41
to Anjar- Bhuj upto Airport Junction from Km 0.000 to Km
65.478 of NH-341
341 59.538 Km 02/01/202
3
83.06 % 29-06-2025 HAM G R Infraprojects Limited Gujarat
23 4L Kodinar – Veraval (Package VI) from km. 222.400 to km. 230.00 (Kodinar Bypass) of NH-8E (NH 51 new) 51 7.6 Km 22/04/202
2
93.94 % 20-09-2023 Item Rate Kalthia Engineering & Construction Ltd. Gujarat
24 4L of Bal Works of  Mahuva to Kagvadar from 100.450
Km. to 140.470 Km. of NH-8E (Pkg- III)
51 40.02 Km 24/03/202
1
94.00 % 23-09-2022 Item Rate KCC Buildcon Pvt. Ltd. Gujarat
25 4L of Bal Works of Talaja – Mahuva from 54.990 km. to
100.450 km. of Old NH-8E (Package-II)
51 45.46 Km 24/03/202
1
97.13 % 24-09-2022 Item Rate Kalthia Engineering & Construction
Ltd.
Gujarat
26 4L PS Divided Carriageway  from Patan (Near Rajpur) to Gojariya From Km 52.000  to Km 128.940 of NH-68 68 76.94 Km 09/03/202
3
69.53 % 07-03-2025 EPC WAGAD INFRAPROJECTS PVT. LTD. –
RACHANA INFRASTRUCTURE LIMITED (JV)
Gujarat