Platform 2 and 3 at Surat railway station to shut for 98 days; 83 trains to halt at Udhna
December 03, 2024
Surat: As part of the ongoing work to upgrade Surat Railway Station into an MMTH (Multi-Modal Transport Hub), platforms 2 and 3 will be closed from December 7th. As a result, more than half of the trains currently stationed at Surat will be shifted to Udhna station. Around 15% of the trains will be moved to the Udhna terminal.
These platforms will remain closed for approximately 98 days. Of the 180 trains that currently halt at Surat Station, 83 will be shifted to Udhna, while 66 will continue to be handled at Surat. Additionally, 31 trains that either start or terminate at Surat will be redirected to Udhna. Premium trains will also have their platforms changed at Surat. The time gap between trains will be reduced during this period.
The work on platforms 2 and 3 will involve tasks such as the construction of COP foundations, roof foundations, lifts, columns, and beams. It is also noteworthy that the redevelopment of platform 4 has been completed at Surat Railway Station, but due to issues with road access and parking in the eastern area, platform 4 remains closed for now. DeshGujarat
Related Stories
Surat Railway Station platforms 2 & 3 closure extended till March 31; Diversion to Udhna to continue
Chain Pulling on the Rise near Surat railway station as 206 trains stop only at Udhana
Western Railway revises halts for these trains from Surat Railway Station to Udhna
Recent Stories
- India vs SL Match
- Free rides on AMTS buses for three days during Diwali
- 100 years of service to nation was our duty, so no celebration is needed: RSS Chief
- Commonwealth Sport Board Recommends Ahmedabad as Host City for 2030 Commonwealth Games
- Gujarat CM to visit Mumbai for listing of SMC's green municipal bonds on NSE